home
Donate now

Menu

The Swiss Open-Air Museum is – finally – getting a schoolhouseConstruction diary schoolhouse Unterheid

The schoolhouse in Unterheid, near Meiringen (BE), is currently being dismantled stone by stone so that it can be rebuilt at the Swiss Open-Air Museum. We’re keeping a construction diary, packed with all the latest about the relocation work, construction progress, the history of the building, background information and other interesting facts about this special project.    

Share page:
Historisches Schulhaus auf Reisen: Der Startschuss für die Translozierung des historischen Schulhauses aus Unterheid ist gefallen.

Construction diary entry no. 5, october 2024Brick by brick– a jigsaw puzzle unlike any other

After being meticulously taken apart brick by brick, the schoolhouse is now being reconstructed just as it was in the past. The bricks, which were separated and marked when the building was dismantled to indicate which storey they were from and which direction they were facing, are taken from where they were being stored outside the museum to the construction site, where they are sorted. Thanks to the detailed plans prepared beforehand, the particularly prominent bricks can be returned to their original position. This is especially important at the corners of the building, as they are very important for the static equilibrium of the schoolhouse. The whole thing resembles a giant jigsaw puzzle in which the masonry is being carefully reassembled.

Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

Almost like dry stone masonry

When the schoolhouse was built in 1830, the quarry stones were not hewn into blocks before being laid into position. This meant that there were hollows in the masonry between the unevenly shaped bricks, which were then filled with slate and mortar, just as they are today. When building the walls, it is also important to ensure that each brick touches at least three others to make sure the building is stable enough. The way the schoolhouse is bricked means that its walls could almost stand by themselves, without mortar, like a dry stone wall. This is because the loads are supported by the bricks themselves and not by the mortar. Nevertheless, mortar is needed to join the bricks together. The pure lime mortar used for the schoolhouse has a higher level of elasticity compared to modern cement mortar, which allows the building to compensate for minor movements in the masonry.

Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

Lime mortar – straight from the construction site

Right next to the construction site is a specially equipped mixing site where the lime mortar is produced. The lime required for the lime mortar was fired in a lime kiln on the Ballenberg site. If you want to learn more about the fascinating process of lime burning, we recommend our article on the lime cycle.

Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

Traditional techniques without any glue or screws

The reconstruction process is being carried out closely in line with historical masonry techniques. While the masons put the individual bricks together to form a stable wall, the carpenters work on the timber elements at the same time. Even during the dismantling process, these elements were carefully examined for damage and analysed to determine which parts needed to be replaced and reconstructed. As is customary at Ballenberg, the carpenters use traditional timber construction techniques. The components are connected using mortices and wooden nails, without any glue or screws.

Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

Construction work is stopping for winter – but the construction diary continues 

As winter approaches, Mother Nature will force us to take a break from construction work. As soon as temperatures drop below 5°C, it will no longer be possible to work with lime mortar and the Unterheid schoolhouse construction site will close for winter. The doors of the Swiss Open-Air Museum will close from 27 October 2024 to 9 April 2025. So why not use the last few days of the season to check out the impressive reconstruction work on site?

Despite the winter break, we will continue to update our blog with monthly reports on the progress of the project, interesting background information and plans for the coming year. So stay tuned and don’t miss any updates on the reconstruction of the Unterheid schoolhouse!

Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

Construction diary schoolhouse Unterheid

  • Der letzte Stein ist abgebaut, das Schulhaus Unterheid ist auf dem Weg auf den Ballenberg.

    Reconstruction is underway – the schoolhouse is being rebuilt brick by brick.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Masons and carpenters work hand in hand during the reconstruction process. The first door frames are already in place.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The hollow spaces between the quarry stones are filled with slate, which is pressed into the mortar.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    The carpenters also follow plans to ensure that every timber component is in its proper place.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    Beams are inspected for damage and some parts are replaced or reconstructed.

  • Als einer der ältesten künstlich hergestellten Baustoffe wurde Branntkalk als Bindemittel im Kalkmörtel in verschiedenen Bereichen eingesetzt.
  • Für Mörtel, Verputz und Kalkanstrich wurden Kalksteine in einem Ofen auf über 1000°C erhitzt und dann nach dem Abkühlen mit Wasser «gelöscht».
  • Für Mörtel, Verputz und Kalkanstrich wurden Kalksteine in einem Ofen auf über 1000°C erhitzt und dann nach dem Abkühlen mit Wasser «gelöscht».
  • Lagerung der Holzelemente vom Schulhaus Unterheid.

    The wooden elements are being stored, and damaged or missing wooden parts are being reconstructed.

  • Das Schulhaus Unterheid ist vollständig abgebaut.

    The building has been completely dismantled.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    The last walls are being dismantled.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Prominent bricks are measured and recorded on the plan.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    The bricks are numbered according to the plan.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Bricks are stored separately by wall and storey.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Bricks are stored separately by wall and storey.

  • Mit der Translozierung vom Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung.

    A piece of wood with a drawing was discovered while dismantling.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Leta Büchi, a qualified excavator, and Patrick Bürgin, project manager for the translocation of the schoolhouse, inspect the structural changes to the jetty.

  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung

    Negative recesses in the windows indicate that they were replaced over the course of time.

  • Das neue Zuhause, das Fundament vom Schulhaus aus Unterheid steht.
  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung historischer Häuser.
  • Historisches Schulhaus auf Reisen: Der Startschuss für die Translozierung des historischen Schulhauses aus Unterheid ist gefallen.
  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung historischer Häuser.
  • Mit dem Schulhaus aus Unterheid aus dem Jahr 1830 erweitert das Freilichtmuseum Ballenberg seine Sammlung historischer Häuser.

The relocation is supported by the Ghelma AG Baubetriebe in Meiringen. Thank you very much!

Ballenberg
Swiss Open-Air Museum

Museumsstrasse 100
CH-3858 Hofstetten bei Brienz

+41 33 952 10 30
info@ballenberg.ch

Opening hours

10 April to 2 November 2025
10 am to 5 pm daily

Annual holiday from 20 December 2024 to 5 January 2025

Follow us